Preliminary Project Schedules
New Campus Center
- Complete Site Visits and Program Definition Phase - May/June 2008
- Schematic Design Phase - June/July 2008
- Design Development Phase - August/September 2008
- Construction Documents Phase - September thru December 2009
- Bidding and Negotiations Phase - January 2009
- Contract Award and Construction Mobilization - February 2009
- Construction Administration Phase begins - March 2009
- Building Enclosure - November 2009
- Building Occupancy - July 2010
Greenhouse/Classroom Facility
- Program Definition Phase - June 2008
- Schematic Design Phase - June 2008
- Design Development Phase - July 2008
- Construction Documents Phase - July/August 2008
- Bidding Phase - September 2008
Construction Phase
- Foundations, Utilities and Greenhouse - October thru December 2008
- Project Balance - January thru March 2009
New Facility Services Building
- Program Definition Phase - June 2008
- Schematic Design Phase - June/July 2008
- Design Development Phase - July/August 2008
- Begin Construction Documents Phase - August 2008
- Bidding/Contract Award for "Foundations and Utilities" - September 2008
- Construction Phase for "Foundations and Utilities" - October/November 2008
- Complete Construction Documents Phase for "Project Balance" - October 2008
- Bidding Phase for "Project Balance" - November 2008
- Construction Phase for "Project Balance" - December 2008 thru July 2009
Classroom Remodeling
- Schematic Design Phase - October/November 2008
- Design Development Phase - November/December 2008
- Construction Documents Phase - December 2008/January 2009
- Bidding Phase/Contract Award - February/March 2009
- Construction Phase - April thru August 2009
To be determined
- Building J Renovations
- Parking Lot Reconfiguration
- Inner Ring Road/Service Road
- Temporary Building Demolition and Site Restoration
- Sidewalks, Paths, Natural Areas Path, Porches
- Landscaping
- Signage