Preliminary Project Schedules
New Campus Center
- Complete Site Visits and Program Definition Phase -
May/June 2008
- Schematic Design Phase -
June/July 2008
- Design Development Phase -
August/September 2008
- Construction Documents Phase -
September thru December 2009
- Bidding and Negotiations Phase -
January 2009
- Contract Award and Construction Mobilization -
February 2009
- Construction Administration Phase begins -
March 2009
- Building Enclosure -
November 2009
- Building Occupancy -
July 2010
Greenhouse/Classroom Facility
- Program Definition Phase -
June 2008
- Schematic Design Phase -
June 2008
- Design Development Phase -
July 2008
- Construction Documents Phase -
July/August 2008
- Bidding Phase -
September 2008
Construction Phase
- Foundations, Utilities and Greenhouse -
October thru December 2008
- Project Balance -
January thru March 2009
New Facility Services Building
- Program Definition Phase -
June 2008
- Schematic Design Phase -
June/July 2008
- Design Development Phase -
July/August 2008
- Begin Construction Documents Phase -
August 2008
- Bidding/Contract Award for "Foundations and Utilities" -
September 2008
- Construction Phase for "Foundations and Utilities" -
October/November 2008
- Complete Construction Documents Phase for "Project Balance" -
October 2008
- Bidding Phase for "Project Balance" -
November 2008
- Construction Phase for "Project Balance" -
December 2008 thru July 2009
Classroom Remodeling
- Schematic Design Phase -
October/November 2008
- Design Development Phase -
November/December 2008
- Construction Documents Phase -
December 2008/January 2009
- Bidding Phase/Contract Award -
February/March 2009
- Construction Phase -
April thru August 2009
To be determined
- Building J Renovations
- Parking Lot Reconfiguration
- Inner Ring Road/Service Road
- Temporary Building Demolition and Site Restoration
- Sidewalks, Paths, Natural Areas Path, Porches
- Landscaping
- Signage