Summer 2009 Parking Projects - Main Campus
During summer 2009, the college will complete several parking projects to help alleviate issues associated with construction projects as part of the college's master plan.
Parking Project - Phase One (May 25 - July 3, 2009)
Parking Lots Closed: North Lot 2 & South Lot 1
Phase One will involve the reconfiguration of North Lot 2, which is the student lot north of J-Building, and South Lot 1, which is the lot south of the C- and D-Buildings. Both lots will be closed during this time and will reopen on July 6.
Parking for Persons with Disabilities
Parking spaces for persons with disabilities currently located in North Lot 2 will be relocated to North Lot 1, the faculty/staff lot. Those spaces currently located in South Lot 1 will be relocated to South Lot 2.
Parking Project - Phase Two (July 6 - August 21, 2009)
Parking Lots Closed: East Lots 2 & 3
Phase Two will involve the reconfiguration of East Lots 2 and 3, which are east of the T-Building. Both lots will be closed during this time and will reopen on August 24.
Parking for Persons with Disabilties
Parking spaces for persons with disabilities currently located in East Lots 2 and 3 will be relocated to the front rows of East Lot 4.