| Project Name |
Progress for the Month of: |
| Replace Insulation on HVAC Duct at City Center |
Feb 08 |
| Design Team |
Design Status |
| J. L. Meece |
Active |
| Award to: |
Tentative Start Date |
| |
|
| Project Description |
| The project scope is to install new insulation
on the exterior duct. |
| Construction Completed |
| J. L. Meece delivered design drawings. |
| Issues/Coordination Concerns |
| Projects have been combined for City Center. |
| Construction Status (30 Day Outlook) |
| JJC to submit comments to J. L. Meece to complete design
drawings including roof drainage repairs.
J. L. Meece to submit design drawings and specifications for bid.
Issue for bid. |