Monthly Progress Report |
|
|
For more information, contact:
Sera Jahn
Project Assistant
Phone: 815 280-2651
Email: sjahn@jjc.edu Return to Projects List
|
| Project Name |
Progress for the Month of: |
| North Campus VMA Box Controls |
Feb 08 |
| Design Team |
Design Status |
| Stanley Consultants |
Active |
| Award to: |
Tentative Start Date |
| International Piping Systems |
|
| Project Description |
| The project scope is to install digital
controlled thermostats to allow a quick response time from the main campus which
is staffed. |
| Construction Completed |
| Notify International Piping System of
Award.
Contractor submitting Contract, Bond and Certificate of Insurance.
Held pre-construction meeting. |
| Issues/Coordination Concerns |
| |
| Construction Status (30 Day Outlook) |
| Contractor submitting required documents. |
| Pictures of Project |
|
|
|
|
|
|
|