Monthly Progress Report |
|
|
For more information, contact:
Sera Jahn
Project Assistant
Phone: 815 280-2651
Email: sjahn@jjc.edu Return to Projects List
|
| Project Name |
Progress for the Month of: |
| K 1000 Lighting System Phase II |
Feb 08 |
| Design Team |
Design Status |
| Stanley Consultants |
N/A |
| Award to: |
Tentative Start Date |
| Block Electric |
N/A |
| Project Description |
| The project scope includes additional
lighting and circuits to control items for the newly installed panel.
Project is necessary to complete the replacement/improvements of the
Theatre Lighting System. Phase II will complete the Lighting
System and add the ability to hang instruments. |
| Construction Completed |
| Project completed. |
| Issues/Coordination Concerns |
| |
| Construction Status (30 Day Outlook) |
| |
| Pictures of Project |
| |
|
|
|
|
|