| Project Name |
Progress for the Month of: |
| Flower Combination Cooler |
Feb 08 |
| Design Team |
Design Status |
| Stanley Consultants |
Active |
| Award to: |
Tentative Start Date |
| Quality Mechanical |
|
| Project Description |
|
The project scope includes replacing the
existing coolers and the wall behind the coolers. The wall and cooler will be
rotated to allow entry off the hallway.
|
| Construction Completed |
| Complete trim around coolers.
Replace defective condensing unit. |
| Issues/Coordination Concerns |
| Completion delayed due to our quality testing. |
| Construction Status (30 Day Outlook) |
| Prepare punch list and complete items.
Close out project. |