| Project Name |
Progress for the Month of: |
| Exterior Emergency Phone Upgrade |
Feb 08 |
| Design Team |
Design Status |
| Stanley Consultants |
N/A |
| Award to: |
Tentative Start Date |
| N/A |
N/A |
| Project Description |
| The project scope is to replace all
existing emergency old style phones with upgraded emergency phone
system. |
| Construction Completed |
| Stanley to continue with design. |
| Issues/Coordination Concerns |
| Reviewing sustainability options. |
| Construction Status (30 Day Outlook) |
| Stanley to continue on design and submit review set. |