| Project Name |
Progress for the Month of: |
| Boilers, Burners and Controls Replacement |
Feb 08 |
| Design Team |
Design Status |
| Stanley Consultants |
Board Approval |
| Award to: |
Tentative Start Date |
| Quality Mechanical |
May 07 |
| Project Description |
| The project scope is to replace control
units operating the boilers with new technology and replace burners with
high efficiency units for energy savings and reliability. |
| Construction Completed |
| Project completed. |
| Issues/Coordination Concerns |
| |
| Construction Status (30 Day Outlook) |
| Close out project. |