Monthly Progress Report |
|
|
For more information, contact:
Sera Jahn
Project Assistant
Phone: 815 280-2651
Email: sjahn@jjc.edu Return to Projects List
|
| Project Name |
Progress for the Month of: |
| A and T Building Carpet Replacement |
Feb 08 |
| Design Team |
Design Status |
| Legat |
Active |
| Award to: |
Tentative Start Date |
| |
|
| Project Description |
| The project scope is to replace the carpet
located in the A and T Concourse with new carpet and install tile in selected
areas. |
| Construction Completed |
| Carpet has a 4-5 week lead time.
Mock up installed. Review with architect.
Establish final scope. |
| Issues/Coordination Concerns |
| |
| Construction Status (30 Day Outlook) |
| Legat to continue design and preparation of bid documents.
Issue for bid in March. |
| Pictures of Project |
|
|
|
|
|
|
|