JJC: Facility Services - Monthly Progress Report

CAMPUS INFORMATION     PROSPECTIVE STUDENTS     CURRENT STUDENTS     BUSINESS & INDUSTRY    SEARCH
 
Facility Services
Home

Project Management
  - Current/Future Projects
  - Upcoming Scheduled Bids
  - Project Forms
  - JJC Master Plan
  - Capital Improvement Project (CRIP) (PDF)
       - 2008
       - 2007

Environmental/Health/Safety
- Meet Our Staff
- Safety Committee Meetings
- Industry Links
- Sector Leader Program
- Ice/Water Rescue
- EHS Photo Gallery
- Important News/Information
- Emergency Response Plan

Custodial
- Use of Facility Policy PDF
- Facility Sched. Use Form PDF
-
Facility Fee Listing

Roads & Grounds

Maintenance

IService Desk
(requests for work orders)
 

JJC Home

 

 
Current & Future Projects at JJC

Images of Main Campus Pedestrian Bridge - to north lots
Pedestrian Bridge
Main Campus

Marquee Signage
Main Campus

Image of Chiller Tower
Chiller Tower
Chiller Replacement 


 
Current Projects  2007 Current Projects 2008 Projected Projects

Current Projects - All campus locations
View - Campus Project Map 2007 PDF (356 KB)
 


 

2007 JJC Current & Projected Projects  All campus locations

Project Name:

Building/Location

Schedule of Work

Weitendorf Agricultural Education Center Weitendorf Center  Completed
     

12.47 Switching Equipment Replacement

Main Campus

May 07 - Sept 07

Boiler Controls and Piping

Main Campus

April 07- Oct 07

Chiller Replacement Design Phase I

Main Campus

May 07

CDL Truck Lot Main Campus N/A
Concourse Bridge Renovation Main Campus Aug 07 - Sept 07

Exterior Signage Phase 4

Main Campus

N/A

Exterior Emergency Phone Upgrade

Main Campus

N/A

Fire Alarm Replacement Phase II Main Campus May 07

Sewer System Repairs Phase II

Main Campus

Completed

Biology/Chemistry Lab

E Building

May 15 - Oct 07

“H” Building Bridge Painting

H Building

N/A

“J” Building Roof Replacement

J Building

Completed

K 1000 Lighting System Phase II K Building Completed
Library Renovation  J Building Jun 07 - Dec 07
V Building Acoustical Ceiling V Building Completed

North Campus Entrance/Parking Lot Repairs

North Campus

Completed

North Campus Ceiling Tile Replacement

North Campus

Completed

Back to Top
 

- 2008 JJC Current & Projected Projects - All campus locations

 

Project Name: Building/Location Schedule of Work
Elevator Cab Replacement at Buildings A/B, D and J. A/B, D and J Buildings Jan
A and T Building Carpet Replacement A and T Buildings N/A
Flower Combination Cooler A Building Dec 07
Early Childhood Passage Doors B Building N/A
Replacement of Entry Door System at Buildings, J, G and B B, G and J Buildings N/A
Auto Shop Air Conditioning C Building N/A
C-G Bathroom Renovations C - G Buildings N/A
C 2021 Server Room A/C Addition C Building N/A
12.47 Switching Equipment Replacement at Substation D Building D Building N/A
J 4052 Reconfiguration J Building N/A
Library Remodeling Phase II J Building N/A
IT Window Glazed Systems J Building Nov - Dec
Buildings T and V Emergency Upgrades T and V Building N/A
T 2026 Remodeling/Rearranging T Building N/A
Prosthetic Laboratory T Building Sept - Dec
Boiler House Roof Replacement Boiler House N/A
Boiler House Ethernet Install Boiler House N/A
Greenhouse Boiler Replacement Greenhouse N/A
Lake Enhancement N/A N/A
Facility Condition Assessment N/A N/A
Substation Air Compressor Replacement Main Campus N/A
North Campus Parking Lot Phase 2 North Campus Completed
North Campus VMA Box Controls North Campus N/A
City Center Remodeling City Center Oct - Dec
Replace Insulation on HVAC Duct at City Center City Center N/A
Repair Roof Drainage at City Center City Center N/A
     
     
     

Back to Top

Return to previous page Return to JJC Home    

Your Future... Your Way... Your Community College

Facility Services
Joliet Junior College, 1215 Houbolt Road, Joliet, IL 60431-8938 (815) 729-9020 ext. 2332
© 2006  Joliet Junior College All rights reserved